HV Substation
Power Transformers
Main LV Distribution Panels and network
Lighting Systems
UPS Network
Early Warning Addressable Fire Detection and Alarm System
PROJECT CHALLENGES
Systems were Re-designed during Construction due to Project Alterations
3000 Light Fittings were Delivered Late and had to be Installed in 2 Weeks
Project was Fast Track
PROJECT FIGURES
2 Mw of Installed Power
15Km of Power Cables installed
500Km of Electrical Wiring Installed
25,000 Electrical Connection Outlets Installed
600 Addressable Devices Installed on the Fire Alarm System